The city council has also confirmed that the scheme is continuing on budget.
A new report confirmed that the main part of the work has already been completed.
Advertisement
Hide AdAdvertisement
Hide AdMark Turley, director of the city council’s services for communities department, said: “Following the ground- breaking ceremony in January, the main ground works, roof and external structure of the building have been completed.
“Contractors are now progressing the remaining internal work, with progress on schedule for the building to be complete in November 2011.
“The new building is due to open in early 2012 once the interior has been fitted.”